Case Study: B&I - Leading Mechanical Contractors

Two major problem areas were hanger placement and spooling. For example, for one building, it took over a week to create 2,500 hangers for the ductwork – a significant amount of manpower and project time. Additionally, B & I wanted help in auto-tagging and with a lineup tool to set up multiple sets of pipes

"One of the most dramatic results has been the time saved in hanger placement. What used to take 40 hours is now down to eight. This has freed up time for the B & I team to take on more projects because tasks can be completed more efficiently."

 

bi case study hanger